When buyers inspect a Dholera Town Planning (TP) Map, almost every map displays Final Plot (FP) numbers, road widths, and zoning colours. However, what most sellers fail to mention is which statutory sanction stage that specific Sub-TP scheme has reached.
Across Dholera SIR’s ~422 sq. km. urbanisable area, the 6 Town Planning Schemes (TP1 to TP6) are divided into 27 Sub-TPs. Understanding the difference between a Draft TP Scheme and a Preliminary TP Scheme is critical—because it determines whether your Final Plot’s shape, location, and road frontage are legally fixed or still subject to adjustment.
- Draft TP Scheme (Tentative FP Layout): Initial planning layout prepared by DSIRDA. Final Plot numbers and boundaries shown on a Draft TP map are proposed—they can shift, resize, or change road orientation during Town Planning Officer (TPO) hearings before Preliminary sanction.
- Preliminary TP Scheme (Legally Fixed FP Boundaries): Once the Town Planning Officer completes landowner hearings, reconstitution, and F-Form allotment and the Gujarat government sanctions the Preliminary TP, physical Final Plot boundaries, net area, and road access become legally binding.
- Final TP Scheme (Financial Settlement): The third stage where incremental contribution / betterment charges and compensation figures are finalized.
Draft vs Preliminary vs Final TP Scheme: Side-by-Side Comparison
Under the Gujarat Town Planning and Urban Development Act, every Town Planning scheme moves through three statutory milestones. Here is how each stage impacts a land or plot buyer:
| Parameter | 1. Draft TP Scheme | 2. Preliminary TP Scheme | 3. Final TP Scheme |
|---|---|---|---|
| Authority Action | Initial zoning, road grid & proposed OP-to-FP layout published | TPO hears landowner objections, finalizes reconstitution & F-Form | TPO finalizes valuation, compensation & betterment charges |
| Are FP Boundaries Fixed? | No — Tentative / proposed only | Yes — Physical FP shape, area & road frontage are legally frozen | Yes — Already frozen at Preliminary stage |
| Can FP Location Shift? | Yes, possible during TPO hearings | No (except rare court/govt variation orders) | No |
| Trunk Infra Rollout | Early planning / phased later | Eligible for road & utility execution (highest in TP 2A & TP 4A) | Full statutory closure |
| Buyer Risk Profile | Higher boundary-shift risk; requires careful agreement clauses | Lower boundary risk; verifiable via F-Form & Sanctioned Map | Lowest statutory TP risk |
TP1 to TP6 & 27 Sub-TPs Overview Across Dholera SIR
Dholera’s six master Town Planning Schemes (TP1–TP6) are broken down into smaller Sub-TP blocks so infrastructure and statutory approvals can advance in manageable phases. In particular, TP 2A and TP 4A—which form the 22.54 sq. km. Activation Area—reached Preliminary sanction first, enabling trunk road and utility construction.
| TP Scheme | Sub-TP Divisions | Key Villages Covered | Sanction & Readiness Profile |
|---|---|---|---|
| TP Scheme 1 | Sub-TPs 1A-1 to 1A-5, 1B (6 Sub-TPs) | Kadipur, Ambli, Bhadiyad, Gogla | Preliminary + Draft Mix Key northern residential & institutional Sub-TPs sanctioned at Preliminary stage; remaining advancing through TPO process. |
| TP Scheme 2 | Sub-TPs 2A, 2B (and sub-sectors) | Kadipur (border), Gogla, Gorasu, Mingalpur, Mahadevpura | TP 2A Preliminary (Activation Core) Houses the ABCD hub and primary Activation Area trunk infrastructure; 2B in phased progression. |
| TP Scheme 3 | Sub-TPs 3A, 3B (and sub-sectors) | Gorasu, Sodhi, Sandhida, Bhimtalav | Phased Preliminary / Draft Central-western industrial & mixed-use corridor progressing in phased Sub-TP stages. |
| TP Scheme 4 | Sub-TPs 4A, 4B (and sub-sectors) | Bavaliyari, Hebatpur, Sangasar, Panchi | TP 4A Preliminary (Activation Core) Covers southern Activation Area and major industrial/semiconductor ecosystem; 4B in phased progression. |
| TP Scheme 5 | Sub-TPs 5A, 5B (and sub-sectors) | Cher, Dholera, Khun, Mundi | Draft / Phased TPO Stage Southern and eastern urban/coastal buffer belt moving through statutory TPO reconstitution. |
| TP Scheme 6 | Sub-TPs 6A, 6B (and sub-sectors) | Dholera, Zankhi, Rajpur, Bhangadh | Draft / Phased TPO Stage Southernmost zone planned for longer-horizon urban and logistics expansion. |
3 Practical Rules Before Buying in a Draft or Preliminary Sub-TP
Rule 1: Verify the F-Form in Preliminary Sub-TPs
If a seller claims the plot is in a Preliminary TP scheme, ask for the Redistribution & Valuation Statement (F-Form) and match the Original Plot (OP) area, net Final Plot (FP) area in sq. meters, and TP map boundaries using our step-by-step Final Plot (FP) verification guide.
Rule 2: Never Treat a Draft FP Sketch as Permanent
If a parcel sits in a Draft Sub-TP, understand that the proposed FP number, plot shape, or road width shown on a draft layout can be modified by the Town Planning Officer before Preliminary sanction. Ensure your sale agreement clearly records the underlying Revenue Survey / Block Number and 7/12 ownership title.
Rule 3: Check NA Order & GujRERA for Private Plotted Schemes
Even inside a Preliminary TP scheme, buying a small residential plot inside a private township requires valid Non-Agricultural (NA) conversion, a DSIRDA-sanctioned sub-plotting layout plan, and GujRERA registration. Run our 15-point property due diligence checklist before paying token money.
Frequently Asked Questions: Draft vs Preliminary TP in Dholera
What is the main difference between a Draft TP and Preliminary TP in Dholera SIR?
Which Dholera TP schemes were sanctioned first at the Preliminary stage?
Is it safe to buy land in a Draft TP scheme in Dholera?
How many total Sub-TPs exist in Dholera SIR?
Explore our complete Town Planning and Map verification resources for Dholera SIR: